Weightmans advised PSI Global in relation to a contractual variation agreement further to a contract for supply and installation of a utilities monitoring system under the specialist IChemE Form of Contract for Minor Works, for works of a chemical engineering nature.
The works related to protection against emissions of potentially toxic gas. We advised on issues in relation to the impact on the work scope, price and programme. Our advice was completed urgently with a response provided to our client within 2 working days of our instruction.